2.2MW Installation underway

2.2MW Installation underway

Main Content

Works are well underway at our 2.2Mw installation on a large distribution warehouse in Coalville, Leicestershire.

 The system comprises of 6600 340w JA solar modules installed with K2 minirail system, connected to 15 Huawei inverters which are connected to 2 LV panels.

 The Great British weather has had an impact on works, with a crane lift being cut short due to wind and repeated heavy rain showers to work around. We remain confident the project will be completed ahead of time, and providing most of the clients electricity demands by August 18th

 