2.2MW Site Continues!

Main Content

Works continue ahead of schedule at our 2.2Mwp install on a large distribution centre in Coalville.

All 6600 modules will be installed by 21st July, with associated electrical works completed by 26th July.

We aim to complete G99/G100 testing on 27th July, over a month ahead of schedule, which will allow the distribution centre to make the most of what will hopefully be a few more months of sunshine!

 